Locker Room at the North Shore Aquatic Center

A Commercial Case Study by CertaPro Painters of Salt Lake City

Ready to make a change?

Schedule an Estimate

Full-Scale Transformation

Our commercial team of painters were recently hired to paint this locker room in the North Shore Aquatic Center in North Ogden, UT. The project came with it’s share of challenges, but our crew left the property with another satisfied customer.

walls

About the Project:

Scope of the Project:

This project involved repainting a commercial locker room facility in North Ogden, Utah. The total painted area was approximately 13,692 square feet.

The scope included:

  • Men’s and women’s locker rooms
  • Shower and bathroom areas in each
  • Two family bathrooms

The facility included block walls, drywall ceilings, crown molding, tiled wall sections, and locker systems requiring detailed prep work around fixtures and tile. Approximately 50 gallons of paint were used to complete the project.

Condition of the Facility:

At the start of the project, the facility was a cold, unheated, and damp existing locker room environment. The walls were visibly dirty and had accumulated buildup consistent with a high-moisture locker room and shower setting.

Additionally, the surfaces presented significant adhesion challenges:

  • The existing coating was no longer VOC compliant and could not be reused due to county regulations.
  • The block walls were dirty and contaminated.
  • Unknown contaminants were discovered on the upper portions of the walls.
  • Previous caulking used in some areas was not paintable.
  • When new paint was initially applied, it failed to adhere and began running off the block walls.

Due to these conditions, the project required extensive cleaning, degreasing, sanding, and the application of a specialty bonding primer to stabilize the surface before proper coating application could begin. Once properly prepared, primed, and cured, the surfaces accepted the finish coat successfully, resulting in a smooth, uniform, and durable finish appropriate for a high-moisture locker room environment.

The transformation was significant — the space went from a cold, damp, and failing surface environment to a clean, bright, professionally finished locker room with a smooth, durable coating designed to withstand high humidity and heavy use.

Preparation Time:

  • 14 hours of prep for each locker room (male and female)
  • 5 hours of prep for each of the two family bathroomsApproximately 38 total hours of preparation for the project

Project Tasks:

  • Extensive surface preparation
  • Power washing the block walls to remove dirt and contaminants
  • Cleaning and degreasing contaminated walls
  • Sanding areas with adhesion failure
  • Addressing non-paintable caulking
  • Bringing in radiant heat to help combat the cold, damp conditions and allow proper curing
  • Application of Sherwin-Williams Extreme Bonding Primer
  • Allowing proper cure time (24–48 hours) before top coating
  • Application of Sherwin-Williams Multi-Surface Acrylic (SW 7006 Extra White in Glossy sheen)
  • Painting walls, ceilings, and crown molding
  • Detailed prep work around lockers and tile

Special Challenges:

The primary challenge was the failure of new paint to adhere to the existing block walls due to unknown contaminants and prior coatings. The paint initially ran down the walls rather than bonding to the surface.

Additionally, the previously used coating was no longer VOC compliant and unavailable. Non-paintable caulking created additional surface prep requirements. These issues required halting application, reassessing the substrate, and implementing a revised preparation and priming strategy. The unexpected adhesion issues added two additional days to the timeline.

Additional Details:

Approximately 50 gallons of Sherwin-Williams Multi-Surface Acrylic (SW 7006 Extra White) in the glossy sheen were used.

Despite significant adhesion challenges and VOC compliance restrictions, the project was successfully completed within a 1.5-week timeframe, delivering a durable, professional finish suitable for a high-traffic commercial locker room environment.