Commercial Case Study
Ques Industries - Cleveland, OH
PROBLEM TO BE SOLVED:
The wall we were contracted to paint had extensive peeling due to moisture issues and multiple layers of paint that were not well applied from previous projects.
PROJECT INVOLVEMENT:
The projects involved removing failing layers of paint that were not well applied in previous projects. It involved using a mixture of high-pressure washing and chemical strippers prior to applying a waterproofing system of Loxon XP.
CHALLENGES, EQUIPMENT AND TECHNIQUES:
This was an active chemical manufacturing facility and this wall was in their only parking/delivery area so crews had to work off hours in OSHA-regulated conditions. We used chemical strippers, ladders, extension poles, a heavy-duty scissor lift, and respirators.
FINAL RESULT:
The project started in October 2022 and took 2 weeks to complete.
Photos from before and after our team got to work can be seen below!