In July 2020, CertaPro Painters® of Springfield, VA was approached by R. L. Travers and Associates, Inc. to provide a proposal for painting 7901 Hill Park Court. As CertaPro’s team surveyed the area, it became clear a second proposal to paint 7905 Hill Park Court was essential for an all-encompassing renewal to the property.

Following submission of the plan, a meeting was scheduled with the building owner to discuss paint colors and any potential changes. When the modified proposal was finalized, the building owner authorized CertaPro Painters® to begin production.

The two buildings combined are over 30,000 square feet. 7901 has nine tenants including retail spaces and 7905 is occupied by one business.

Public facing sections after cleaning

lift painting by CertaPro

CHALLENGES

Projects of this magnitude often present their own unique set of hurdles. Communication among the team and coordination with the building owner and tenants was vital. Ensuring occupants that distractions and interference would be mitigated was a key cog in the project’s success.

High and hard-to-reach areas necessitated the need for a lift to efficiently complete tasks. Metal and brick sections sat above the bay doors that would have been cumbersome to refinish without the proper equipment. The weather also presented a problem. Rainfall caused operations to halt mid-week, adding days to the projected timeline.

CONDITIONS

  • Dirt Accumulation – Dirt and grime had built up on the exterior of the building over the years
  • Worn Paint – Paint on the side walls and metal sections had begun to wear down due to continuous exposure without proper upkeep
  • Deteriorated Protections – Paint was chipping and old caulking needed to be renewed to reseal vulnerable sections of the buildings

PROJECT INVOLVEMENT

  • Preparation – All surfaces of 7901 & 7905 were sanded, caulked, and masked before painting began. The buildings were also power washed to remove the layers of dust and dirt that covered the exterior.
  • Painting – Painting commenced on September 19, continuing through Sept. 30. The project took longer than expected due to inclement weather. CertaPro’s professionals crafted a plan that would put an emphasis on weekend painting, offering relief for the tenants from large-scale cleaning and painting being completed in high-traffic areas during work hours. Most weekday work was saved for touchups and completing more discrete sections of the property.

PROJECT TIMELINE – Approximately 11 Days

BEFORE PHOTOS

Before the project began, CertaPro Painters® of Springfield, VA surveyed the area and gathered images of sections that needed to be cleaned and painted.

Outdated Commercial Exterior

Outdated Commercial Exterior

The exterior of both buildings were covered in worn paint and layers of dirt that needed to be removed.

Faded Brick & Metal

Faded Brick & Metal

The brick walls and decorative metal sections were outdated, causing them to fade over time.

Dirty & Worn Corners

Dirty & Worn Corners

The corners showed how the painted and brick walls were both susceptible to wear over time.

Dirty Side Walls

Dirty Side Walls

The layers of dirt and grime covering the brick side walls was noticeable from a distance.

Unmaintained Back Walls

Unmaintained Back Walls

The back walls of the property needed extensive cleaning and clearing.

WORK IN PROGRESS

Pictures were taken of the CertaPro Painters® crew using the lift to efficiently complete higher sections of the property.

Lift For Project Completion

Lift For Project Completion

CertaPro Painters® used a lift to make sure all sections of the building were properly completed.

Power Washing

Power Washing

The lift was used to complete the power washing efforts for the whole exterior of both buildings.

High-Area Cleaning & Painting

High-Area Cleaning & Painting

The lift comfortably allowed CertaPro's experts to reach the sections above the bay doors.

THE FINAL RESULT

After the project was completed, CertaPro Painters® gathered photos of the cleaned and painted exteriors. The dirt was removed and painting was completed on lintels, bay doors guides, security doors, bollards, concrete sections, and decorative metal pieces.

Fully Renewed Exterior

Fully Renewed Exterior

The exterior of both buildings were cleaned and painted to elevate the appeal of the property.

Detailed Painting

Detailed Painting

CertaPro's professionals also painted smaller sections within the brick to create a new and uniform look.

Cleaned & Painted Walls

Cleaned & Painted Walls

CertaPro's team power washed the brick walls and repainted the block side walls to elevate their appeal.

Repainted Maintenance Doors

Repainted Maintenance Doors

The maintenance doors surrounding the buildings were repainted to add a new feel to the exterior.

Painted Bollards

Painted Bollards

All sections of the exterior received attention, including a new coat of paint to the safety bollards.