Turn Stone Industrial in Winchester, KY
by CertaPro Painters® of Lexington, KY
Challenges
This project had many challenges to it. Coordinating lift moves with the facility around incoming & outgoing shipments, storage yard material & terrain, & weather.
CONDITIONS
Surfaces were dirty, old factory paint, lots of holes & marks from previous signage etc.
PROJECT INVOLVEMENT
- Preparation – This project involved pressure washing, caulking, siding repairs and painting
- Painting – This project required2 – 60′ boom lifts.
PROJECT TIMELINE – The project started in October of 2020 and took 2 Months to complete.
BEFORE PHOTOS
Before the project began, CertaPro Painters® of Lexington, KY team took pictures of the exterior challenges that we faced prior to painting Turn Stone Industrial.
THE FINAL RESULT
After the project was complete, CertaPro Painters® of Lexington, KY gathered images of the new finish of the building.