In December 2021, CertaPro Painters® of East Tennessee was contracted to paint the entire interior of a large Boys & Girls Club facility, including the Youth Side, Early Child Phase & the Main Hall. The building is located in Knoxville, Tennessee about 15 minutes from Downtown.
After many years of use from many children within the community, the interior walls and trim were in need of a fresh coat of paint. We painted the entire interior facility to include the Main Hall, Youth Side & Main Hall. Changing wall and trim colors throughout.
The project involved prep and repainting to all walls to include: filling in anchor & screw holes, light sanding to walls to remove residue, and scuff sanding any peeling coatings to a firm base.
Due to the nature of this project, the biggest obstacle was the two-week timeline given by the customer. The child care facility closed the building through the December holidays. With pristine time management and two of our expert crews, we were able to complete the painting to their entire facility within their timeline with ease.
BEFORE PHOTOS
Before the project began, CertaPro Painters® of East Tennessee surveyed the area and documented sections that would require their attention.
As you can see, this wall and doorway desperately needed to be scraped and repainted.
This is the entrance of the building prior to any work being done.
This is a photo of the window casing prior to refinishing.
Here you can see the interior of the building prior to any work being done.
As you can see, the paint here was chipping in several places.
In Progress Photos
CertaPro Painters® gathered images while working on the Boys & Girls Club Facility in Knoxville, TN to show how the process used to complete their work.
In this photo, you can see one of our experts applying the first coat of paint.
Knoxville Boys & Girls Club
In this image, you can see where our painters have begun to apply the first coat of paint to the left side of the hallway.
In this photo, one of our experts is using a roller to apply this semi gloss paint. For a building that sees so many children, this is ideal because it's easier to clean!
Teamwork is a vital part of any painting project. Here, you can see one of our painters applying painter's tape while his expert team mate follows along behind.
In this photo, the bathroom is getting a fresh coat of primer prior to being painted.
In preparation of applying the paint, this expert is doing the brush work that the roller can't reach.
THE FINAL RESULT
After the project was completed, meticulously went over the finished areas of the Boys & Girls Club Facility to make it meet their high standards.
In this finished photo, the expert quality paint job is apparent. Notice the lack of splotches and how even the paint job is.
Here is a photo showing the finished trim on the interior window.
Note how smoothly the paint has been applied to this transom window's trim.
Drop cloths are an important part of any painting project, to protect things such as carpet.
Once the painting project has been completed, our expert painters begin clean up.
This bathroom received a fresh coat of paint, as seen in the photo above.
Project Information
By clicking next or submit you agree to receive phone, email, or text communication from us per our Terms of Use and Privacy Policy. Message/data rates apply. We do not share information with third parties or marketing services. By submitting, you authorize Certa ProPainters to reach out via phone, email, or text for explicit information about project needs. We will never share your personal information with 3rd parties for marketing purposes or spam you. You can opt out at any time. Message/data rates apply. Consent is not a condition of purchase.