Ready to make a change?

Schedule an Estimate

1. Describe the condition of the facility/surfaces at the time work began.
Built in 1999 this 2,650 sq ft Colonial was for the most part in very good condition. But its dated gingerbread trim and earthy color prevented it from being all it could be.

2. What did the project involve? (painting, drywall/light carpentry repairs, etc.)
Removal of decorative trim on gables, touch up to siding damaged by extreme sun reflection, full color update to vinyl and wood siding, frieze boards and window frame.

3. When did the project take place (month, year)?
July 2025

4. How long did the project take, start to finish?
2 weeks

5. Were there any special challenges involved?
Technical ladder set-ups. Safety tie-off on roof.

6. Did the project require any special equipment or techniques?
Graco 695 airless sprayer.

Before

Before

In Progress

In Progress

After

After