The Haven Building Complex

Ready to make a change?

Schedule an Estimate

Multi-Unit Apartment Painting Project in Philadelphia

PROBLEM TO BE SOLVED:

Multi-unit projects like these require careful coordination with property managers and residents, a communication plan was used to streamline this process. Some condos had issues like rotting wood, peeling paint or other imperfections that needed to be addressed.

Additionally many of the buildings had considerable height. Painting these buildings required appropriate safety precautions be taken by crew and management.

This project started in April of 2020 and ended in June 2020.

CONDITIONS:

Peeling Paint – washing, scraping, and spot priming of bare areas of wood.
Failing Caulking – CertaPro addressed all caulking needs where gaps existed in-between two wood substrates.
Rotten Wood – replaced all rotten wood that was noted prior to the start of the project and after additional repairs were discovered and approved by the client.
Positive Lead Paint Tests – All work was done in accordance to EPA Lead Preparations.

PROJECT INVOLVEMENT:

Prep – Clean and prep all surfaces for paint, fix issues with caulking, rotted wood, and peeling paint.
Paint – All interior common spaces and exteriors of all 45 units in this three story historic building.